2022 Triview Metro District Asphalt Paving Project Schedule

Broken Timber Trail

Crack Repair (Saw Cutting)     1 Day               Friday (5/6/22)
5” Crack Repair Patching        1 Day               Monday (5/09/22)
Edge Milling                            1 Day               Monday (5/16/22)
2” FDA Fiber Overlay              1 Day               Thursday (5/19/22)

Kitchener Way

Crack Repair (Saw-Cutting)     1 Day               Friday (5/6/22)
5” Crack Repair Patching        1 Day               Tuesday (5/10/22)
Full Width Milling                   1 Day               Tuesday (5/17/22)
2” FDA Fiber Overlay              1 Day               Friday (5/20/22)

Crosswalks

Installed the week of 5/23/22

*Schedule dates are weather permitting. Schedule will be revised if weather delays occur.  