2022 Triview Metro District Asphalt Paving Project Schedule
Broken Timber Trail
Crack Repair (Saw Cutting) 1 Day Friday (5/6/22)
5” Crack Repair Patching 1 Day Monday (5/09/22)
Edge Milling 1 Day Monday (5/16/22)
2” FDA Fiber Overlay 1 Day Thursday (5/19/22)
Kitchener Way
Crack Repair (Saw-Cutting) 1 Day Friday (5/6/22)
5” Crack Repair Patching 1 Day Tuesday (5/10/22)
Full Width Milling 1 Day Tuesday (5/17/22)
2” FDA Fiber Overlay 1 Day Friday (5/20/22)
Crosswalks
Installed the week of 5/23/22
*Schedule dates are weather permitting. Schedule will be revised if weather delays occur.